Offered by:
Department of Chemical Engineering
(KT) |
Prerequisite: C3630/36230 eller tilsvarende |
Recommended semester:
8th semester |
Limitation: Max. 18 |
Scope and form: Instruction of the class and exercise in 2-3 persons team. |
Examination:
Evaluation of reports
(13 point scale
) |
Contact person: |
Sten Bay Jørgensen, KT, Building 229, Tel. +45 4525 2872 |
|
Aim: To teach the participants to:
- Plan and execute start-up of the chemical plant.
- Apply a Distributed Control System for chemical plant operation.
- Document operation of a chemical plant. |
Contents: Introduction to a practical plant, e.g. an energyintegrated distillation column incl. measurement, control and safety supervision system. Calibration proce-
dures for measurements. Construction of control loop diagrams. Introduction to plant control hierachy, incl. safety aspects. Introductin to the principles for how production planning and scheduling affects plant optation. Operator controlled start-up, operation and shut-down are executed. In addition an automated start-up using e.g. Fuzzy Control is executed. |